January 2026RIOT
Riot Platforms signs $1B AMD data center lease
First hyperscale data center lease at Rockdale, Texas with AMD. 10-year agreement for 25 MW with $311 million initial value, up to $1 billion with three 5-year extensions. AMD holds expansion rights to 200 MW total. Riot acquires 200 acres of Rockdale land for $96 million, funded by selling 1,080 BTC. Establishes 1.7 GW Texas data center portfolio.
Contract value$311M-$1B
Capacity25-200 MW
January 2026APLD
Applied Digital breaks ground on Delta Forge 1
Groundbreaking on 430 MW AI Factory campus in strategic southern U.S. market. Two 150-MW facilities spanning 500+ acres, designed to support 300 MW critical IT load. Leverages proprietary AI Factory blueprint refined at Polaris Forge. In discussions with prospective third investment-grade hyperscaler customer. Initial operations expected mid-2027.
Utility power430 MW
Target onlineMid-2027
January 2026GLXY
Galaxy Digital receives ERCOT approval for 830 MW expansion
Completes Large Load Interconnection Study for additional 830 MW at Helios campus in West Texas. Total ERCOT-approved capacity reaches 1.6 GW. Construction underway for Phase 1 delivery to CoreWeave in H1 2026. Campus expansion potential grows to 3.5 GW with additional land acquisitions.
New approval830 MW
Total approved1.6 GW
February 2026WULF
TeraWulf acquires Kentucky and Maryland infrastructure sites
Strategic acquisitions add 1.5 GW to portfolio. Kentucky site in Hawesville offers 480 MW with immediate power access, on-site substation, and 250+ buildable acres. Maryland acquisition of Morgantown Generating Station includes 210 MW operational generation with expansion potential to 1 GW and 250 buildable acres near Washington D.C. Total portfolio reaches 2.8 GW across five sites with 643 MW contracted and 2.2 GW owned pipeline.
Capacity added1.5 GW
Total portfolio2.8 GW
February 2026GLXY
Galaxy Digital Q4 2025: Phase I delivery imminent, Phase II construction started
Q4 2025 earnings confirm first Helios data hall delivery to CoreWeave by end of Q1 2026. Full 133 MW Phase I on track for H1 2026. Phase II construction already underway with earthwork, concrete, steelwork, and long-lead equipment orders placed. Additional 1.8 GW in ERCOT applications beyond approved 1.6 GW. Management describes Helios as "first step" in multi-gigawatt, multi-tenant, multi-campus platform vision.
Phase I133 MW Q1
Pipeline1.8 GW pending
February 2026CIFR
Cipher Mining closes $2B notes for Black Pearl at 6.125%
$2 billion senior secured notes due 2031 priced at 6.125%, one full point below the Barber Lake offering. 6.5x oversubscribed with $13 billion in orders across 200+ accounts. Fully funds Black Pearl construction. Includes $232.5M reimbursement of prior equity contributions. Three bond offerings now total $3.73 billion.
Notes$2.0B at 6.125%
Total debt raised$3.73B
February 2026CIFR
Cipher rebrands to Cipher Digital, sells JV mining sites to Canaan
Formal rebrand reflects completed pivot from Bitcoin mining to HPC infrastructure. Sold 49% interests in Alborz, Bear, and Chief mining JVs to Canaan in all-stock transaction. Bitcoin holdings reduced to 1,166 BTC with full exit planned by year-end. Only remaining mining operation is Odessa (207 MW, $0.028/kWh PPA through July 2027).
February 2026CIFR
Cipher Q4 2025: Construction on track, $669M NOI projected
Q4 earnings confirm both Barber Lake and Black Pearl on schedule and on budget. Management discloses $669M average annualized NOI from Oct 2026 through Sep 2036, rising to $754M by 2035. No additional equity anticipated for contracted developments. Unrestricted liquidity $754M. Pipeline expands to 3.4 GW with Stingray (100 MW) in advanced lease negotiations, Ulysses (200 MW, Ohio) with hyperscalers in diligence.
Projected avg NOI$669M/yr
Liquidity$754M
February 2026IREN
IREN Q2 FY26: $3.6B GPU financing, 1.6 GW Oklahoma campus
Q2 FY26 results show revenue miss ($185M vs $281M consensus) as Bitcoin mining declines faster than AI Cloud ramps. AI Cloud Services at $17M, up from $7M. Secured $3.6B GPU financing for Microsoft contract at sub-6% interest. Announced new 1.6 GW Oklahoma data center campus with power from 2028. Total secured power exceeds 4.5 GW. Prince George has $400M ARR contracted with $500M+ in negotiation.
GPU financing$3.6B
Total power>4.5 GW
February 2026NBIS
Nebius announces 9 new sites, surpasses 2 GW contracted power
Q4 2025 earnings reveal expansion from 7 to 16 global sites with 9 new locations across Missouri, Alabama, Oklahoma, Minnesota, France, Israel, and the UK. Total contracted utility power exceeds 2 GW, ahead of the >2.5 GW year-end target set in November. Target raised to >3 GW by year-end 2026. Majority of new capacity from owned data centers. B300 GPU deployment underway at new sites. ARR hits $1.25B, beating $900M-$1.1B guidance by 25%.
Total sites16
Contracted power>2 GW
March 2026APLD
Applied Digital prices $2.15B notes at 6.75% for Polaris Forge 2
Subsidiary APLD ComputeCo 2 LLC prices $2.15 billion of 6.750% senior secured notes due 2031 at 98% issue price. Proceeds fund 200 MW critical IT load at Polaris Forge 2 in Harwood, North Dakota. Notes secured by first-priority liens on substantially all subsidiary assets. Applied Digital provides completion guarantees. Offering closed March 10. Combined with $2.35B Polaris Forge 1 notes (9.25%), total project-level debt reaches $4.5B. Coupon compression from 9.25% to 6.75% in four months reflects execution confidence.
Notes$2.15B
Coupon6.75%
Total project debt$4.5B
March 2026NBIS
Nebius signs $27B Meta contract, largest in thesis
Five-year AI infrastructure agreement with Meta valued at up to $27 billion. $12 billion dedicated capacity across multiple locations, plus up to $15 billion additional available compute. One of first large-scale NVIDIA Vera Rubin deployments. Delivery begins early 2027. Expands November 2025 $3B agreement that was constrained by supply. Combined with Microsoft $17.4B, total contracted revenue exceeds $44B. Single contract exceeds pre-announcement market cap of ~$25B.
Contract value$27B
Total contracted$44B+
March 2026WULF
TeraWulf secures $500M bridge facility for Hawesville
364-day, $500 million delayed-draw senior secured bridge credit facility led by Morgan Stanley. Finances construction and development of Hawesville, Kentucky data center acquired February 2, 2026. First dedicated financing for the KY site. $100 million minimum liquidity covenant. Capital formation continues to pace site acquisition.
Facility$500M
Term364-day
March 2026NBIS
Nebius closes $4.34B convertible notes, fully funds 2026 capex
Proposed $3.75B offering on March 17, one day after Meta contract. Demand drove upsizing. Closed March 20 at $4.34B total: $2.59B of 1.25% notes due 2031, $1.75B of 2.625% notes due 2033. Nebius goes from zero debt to $4.34B. Combined with NVIDIA $2B equity and Meta prepayments, management states $16 to $20 billion 2026 capex is fully funded.
Notes$4.34B
2026 capex plan$16-20B
March 2026NBIS
Nebius approved for 1.2 GW Missouri campus, announces $10B Finland site
Independence, Missouri City Council approves Chapter 100 incentive for largest US AI factory campus: up to 1.2 GW on approximately 400 acres, over $650M in PILOT payments across 20 years. Separately, Nebius announces $10 billion data center in Lappeenranta, Finland with 310 MW capacity and first delivery in 2027. Largest site outside the US.
Missouri1.2 GW
Finland310 MW
March 2026CIFR
Cipher Digital signs third campus lease, closes $200M revolver
Executes 15-year lease with undisclosed investment-grade hyperscale tenant for third data center campus at an existing site. Contract value undisclosed. Third hyperscaler-grade counterparty in under a year. Separately closes $200M syndicated revolving credit facility with $50M accordion, led by Morgan Stanley, priced at SOFR +1.25% to 1.75% with leverage-tied step-downs.
Lease term15 years
Revolver$200M
Counterparties3
April 2026GLXY
Galaxy delivers first Helios data hall to CoreWeave; Q1 2026 reported
First data hall at Helios delivered to CoreWeave April 2026; revenue recognition begins. Phase I on budget and on schedule for 133 MW of delivery in Q2 2026 against 526 MW critical IT load commitment, anticipated annual revenue exceeding $1B, and lease-level EBITDA margins of approximately 90% across the 15-year base term. Phase II 260 MW greenfield development underway with deliveries expected H1 2027. Q1 2026 GAAP net loss of $216M ($0.49/share) driven primarily by digital-asset MTM as crypto market cap fell ~20%. Adjusted EBITDA -$188M, narrowed by approximately one-third sequentially. Total assets $9.99B; equity $2.78B; cash and stablecoins $2.6B. Repurchased 3.2M Class A shares for $65M; completed delisting from TSX, consolidating on Nasdaq. Post-quarter, BlackRock selected Galaxy as approved validator for iShares Staked Ethereum Trust ETF.
Phase I commit526 MW
Q2 delivery133 MW
Equity$2.78B
April 2026APLD
Applied Digital signs $7.5B Delta Forge 1 lease with second IG hyperscaler
15-year lease at Delta Forge 1 with U.S.-based high investment-grade hyperscaler covering 300 MW of critical IT load and approximately $7.5 billion in contracted revenue. The campus spans more than 500 acres at 430 MW total approved capacity in a strategic southern U.S. market. Initial operations anticipated mid-2027. Tenant becomes Applied Digital's second U.S. investment-grade hyperscaler and third hyperscaler counterparty across three AI Factory campuses. Total contracted lease revenue rises from approximately $16B to over $23B; more than 50% of contracted revenue now backed by investment-grade counterparties. Concurrent with the lease, Applied Digital expects to enter into an up to $300M senior secured bridge facility for the 150 MW Polaris Forge 1 Building 3 plus an up to $300M senior secured revolving credit facility.
Lease value$7.5B
Capacity300 MW
Total contracted$23.5B
April 2026APLD
Applied Digital Q3 FY26: $71M HPC revenue, first full quarter at 100 MW
Quarter ended February 28, 2026. Revenue $126.6M, up 139% year over year, beating consensus ($75.5M) by 68%. HPC Hosting generated $71M: $44.1M base rent, $18.9M tenant fit-out, $8.1M power pass-through. HPC segment operating profit $17.6M. Data Center Hosting (crypto) $37.5M with $13.9M segment operating profit. Adjusted EBITDA $44.1M. Adjusted net income $33.2M, $0.09 per share, versus consensus loss of $0.14. Cash $2.1B, debt $2.7B at quarter end; pro-forma debt $4.85B including $2.15B PF2 notes closed March 10. Total assets $6.25B, equity $1.58B. CoreWeave SPV upgraded BB to A3 with parent guarantee and $50M LOC. Applied Digital also took 10% equity in Base Electron for up to 1.2 GW of Dakotas natural gas generation.
Revenue$126.6M
HPC revenue$71M
Adj. EBITDA$44.1M
April 2026IREN
IREN Sweetwater 1 substation energization
1,400 MW bulk power station (345kV/138kV) energized at Sweetwater Hub in West Texas. One of largest digital infrastructure developments in the United States. Foundation for multi-gigawatt AI campus. Data hall delivery cadence of approximately 50 MW per month begins post-energization.
April 29, 2026INDUSTRY
Hyperscaler print night validates AI capex acceleration
Microsoft Azure +40% in Q3 FY26, beating the 37 to 38% constant-currency guide ceiling. Google Cloud accelerated to +63% with backlog nearly doubling quarter over quarter to over $460 billion. AWS hit +28%, its fastest in 15 quarters, and disclosed a new ~2 GW Trainium commitment from OpenAI ramping in 2027 on top of Anthropic's reaffirmed up-to-5 GW Trainium commitment. Meta raised 2026 capex guide from $115 to $135 billion to $125 to $145 billion. Each hyperscaler confirmed capacity is the limiter on cloud growth, not demand. Aggregate 2026 hyperscaler capex now sits near $600 billion.
Azure growth+40%
Google backlog$460B+
2026 capex~$600B
April 30, 2026RIOT
Riot Q1 2026: First 5 MW delivered to AMD; 50 MW total commitment
First 5 MW delivered to AMD on schedule in January 2026. AMD exercised the 25 MW expansion option, bringing Rockdale to 50 MW total contracted critical IT capacity. Combined contract value approximately $636 million with $510 million NOI on the deployed footprint; potential to over $1.6 billion with extension options. Annualized lease revenue run-rate target $37.8M exiting 2026, $55.6M exiting 2027 at 80%+ NOI margins. Corsicana redesigned to 168 MW per building, a 50% capacity increase for the same capital spend through enhanced density and layout consolidation. CFO Jason Chung framing on the call: for the first time, the top line includes contracted lease revenue from an investment-grade tenant. Q1 revenue $167M, GAAP net loss $500M including $326.7M non-cash BTC mark-to-market. Stock +12.2% post-print.
AMD capacity50 MW
Contract value$636M
Run-rate exit-2027$55.6M
May 1, 2026NBIS
Nebius agrees to acquire Eigen AI for $643M
Nebius agrees to acquire Eigen AI for $643 million, integrating Eigen's inference and model-optimization technology into the Nebius Token Factory managed-inference platform. Eigen specializes in inference and model optimization. The acquisition advances Nebius from IaaS to a higher-margin PaaS layer, adding a differentiation vector pure GPU cloud operators cannot easily replicate.
Acquisition$643M
LayerToken Factory
May 5, 2026APLD
Applied Digital completes ChronoScale spin-off; CHRN trades on Nasdaq
Cloud business contributed to EKSO Bionics, which renamed to ChronoScale Corporation; CHRN trades on Nasdaq Capital Market beginning May 5. Applied Digital retains approximately 97% ownership: 138 million shares for the contribution plus $15.75 million for an additional 1.4 million shares. APLD now operates as a pure-play data center and HPC hosting platform. The day prior, on May 4, APLD closed a $300 million Goldman-led senior secured bridge facility (SOFR + 275 bps, 364-day, project-asset secured) to fund Polaris Forge 1 Building 3.
CHRN ownership~97%
Bridge facility$300M
Bridge spreadSOFR+275
May 5, 2026CIFR
Cipher Digital Q1 2026: Contracted revenue reaches $11.4B, 907 MW operating + contracted
Contracted revenue rose to $11.4 billion across three IG hyperscale leases. Average annualized NOI of $787 million expected from October 2026 through September 2036, with $892 million targeted by 2035. Operating and contracted capacity reached 907 MW. Development pipeline 3.3 GW prioritized for HPC, with priority sites Reveille and Ulysses holding interconnection approvals targeting 2027 energization. Q1 unrestricted cash and equivalents $715 million; $200 million revolver remains undrawn. Q1 revenue $34.8M reflecting planned mining wind-down at Black Pearl. Stock +23.5% post-print.
Contracted$11.4B
Avg NOI$787M
Op+Contracted907 MW
May 5, 2026INDUSTRY
AMD Q1 2026: Data center revenue +57%, Q2 guide above consensus
Revenue $10.25B (+38% YoY), beating $9.89B consensus. Data center revenue $5.8B, +57% YoY (acceleration from +39% in Q4 2025). Q2 guide $11.2B versus $10.52B consensus. Lisa Su: "Data Center now the primary driver of our revenue and earnings growth."
Revenue$10.25B
Data center+57%
Q2 guide$11.2B
May 6, 2026INDUSTRY
Anthropic signs $45B compute deal with SpaceX/Colossus
Three-year, $45 billion compute agreement using SpaceX/xAI Colossus 1 capacity in Memphis (220,000+ NVIDIA GPUs), adding 300 MW of capacity within a month. Largest single AI compute contract on record. Breaks the two-supplier framing for Anthropic, which sits on top of the previously disclosed up-to-5 GW AWS Trainium commitment and reported $200B Google commitment.
Contract$45B / 3yr
Added capacity300 MW
May 6, 2026RIOT
Riot and Terrestrial Energy sign MOU for up to 4 GW nuclear-paired data centers
Non-binding memorandum of understanding to develop up to 4 GW of nuclear-powered data center capacity using Terrestrial Energy's Integral Molten Salt Reactor (IMSR) plants at 390 MW each. Candidate sites in Texas (Rockdale, Corsicana) and Kentucky. IMSR deployment targeted early 2030s; natural gas bridge generation as accelerated alternative. No dollar terms disclosed.
Capacity (target)up to 4 GW
StatusNon-binding
May 7, 2026IREN
IREN signs $3.4B NVIDIA cloud agreement and 5 GW DSX partnership; Q3 FY26 reported
Five-year, $3.4 billion managed GPU cloud services agreement with NVIDIA at Childress (60 MW air-cooled Blackwell). Strategic partnership designates Sweetwater (Texas) as flagship NVIDIA DSX deployment across up to 5 GW of IREN's global pipeline. NVIDIA receives five-year warrant to purchase 30 million IREN shares at $70 strike, implying up to $2.1 billion in additional equity investment subject to regulatory approval. IREN also announced acquisitions of Nostrum (490 MW grid-connected Spain platform with gigawatt-plus pipeline) and Mirantis (orchestration software). Q3 FY26 revenue $144.8M; net loss $247.8M including $140.4M hardware decommissioning impairment as legacy mining retires. Sweetwater 1 substation energized on schedule. ARR target for end-CY26 raised from $3.4B to $3.7B.
NVIDIA contract$3.4B / 5yr
NVIDIA warrant$2.1B
DSX deploymentup to 5 GW
May 7, 2026INDUSTRY
CoreWeave Q1 2026: Backlog reaches $99.4B, $40B+ new commitments in single quarter
Revenue $2.078B (+112% YoY). Revenue backlog reached $99.4 billion (up from $55B at IPO), with more than $40 billion in new commitments signed in Q1 and ten customers now individually committed at $1 billion or more. Active power surpassed 1 GW; contracted power exceeded 3.5 GW (+400 MW added in quarter). 2026 capex raised to $31-35 billion (from $30-35B). Reaffirmed $12-13B 2026 revenue guide. Net loss widened to $740M on continued infrastructure ramp.
Backlog$99.4B
Q1 new commitments$40B+
Contracted power3.5+ GW
May 8, 2026WULF
TeraWulf Q1 2026: Lake Mariner 60 MW energized for Core42; HPC revenue overtakes mining
Revenue $34.0M ($21.0M HPC lease, $13.0M digital asset). First quarter in which HPC lease revenue exceeded digital asset revenue. Net loss $427.6M. Adjusted EBITDA negative $4.1M. Cash and restricted cash approximately $3.1B. Lake Mariner energized 60 MW of critical IT load for Core42 with lease revenue commencing. CB-3 near completion; CB-4 and CB-5 on track for 2026 deliveries. Hawesville, Kentucky (480 MW grid-connected) confirmed via Justified Data subsidiary with 250+ buildable acres.
HPC lease revenue$21.0M
Lake Mariner live60 MW
Cash + restricted$3.1B
May 13, 2026NBIS
Nebius Q1 2026: $399M revenue (+684% YoY), 2026 capex guide jumps to $20-25B
Revenue $399 million (+684% YoY); AI cloud segment $390M (+841%). Adjusted EBITDA $130M at 32% margin; AI segment 45% margin. ARR run rate $1.9 billion. 2026 guidance raised across the board: revenue $3.0-3.4B, year-end ARR $7-9B, full-year adjusted EBITDA margin approximately 40%. 2026 capex guide jumped from $7B to $20-25B driven by 2027 demand pre-commitments. Meta structure clarified: $12B firm dedicated + $15B option exercisable at Nebius discretion. New Pennsylvania 1.2 GW owned site (first 250-300 MW end-2027, full capacity by 2030). Contracted power exceeds 3.5 GW with >75% owned.
Revenue (Q1)$399M
2026 capex guide$20-25B
ARR run rate$1.9B
May 18, 2026GLXY
Galaxy receives BitLicense and Money Transmission License from NYDFS
GalaxyOne Prime NY granted BitLicense plus Money Transmission License from the New York State Department of Financial Services. Authorizes trading, custody, advisory, asset management, staking, and tokenization services to a regulated U.S. counterparty footprint. Galaxy now holds 50+ licenses globally with approximately $9 billion in client AUM. Corporate development, not infrastructure-thesis core.
Client AUM$9B
Global licenses50+
May 18, 2026INDUSTRY
CoreWeave closes $3.1B DDTL 5.0 HPC-backed loan facility
First publicly syndicated HPC-backed delayed-draw term loan: $3.1 billion at SOFR + 4.50% (priced 50 bps tighter than initial talk), Ba2 (Moody's) / BB+ (Fitch), matures November 15, 2031. Filing explicitly states proceeds support deployment for "two large, non-investment-grade customers." YTD capital raised crossed $20 billion. Material disclosure for counterparty-risk analysis on operators with CoreWeave as primary counterparty (APLD, GLXY).
Facility$3.1B
SpreadSOFR+450
CRWV YTD capital$20B+
May 18, 2026INDUSTRY
DOE Emergency Order 202-26-23: PJM curtailment authority for data centers
Energy Secretary issued emergency order authorizing PJM to direct backup generation at data centers and large industrial loads to operate as last resort before EEA 3 / firm load shed. Triggered by Mid-Atlantic heat plus more than 40 GW of planned plant outages, with reserves projected below 5,800 MW. Effective three days, May 18-20. First federal action that operationalizes data centers as a grid resource. Bear case (grid stress is real) and rebuttal (campuses with backup generation become peaking-capacity assets) both supported.
Reservesbelow 5,800 MW
Planned outages40+ GW
May 20, 2026NBIS
Nebius signs Bloom Energy fuel-cell master agreement up to $2.6B
Master fuel-cell capacity agreement with Bloom Energy covering approximately 250 MW guaranteed (328 MW installed) and up to $2.6 billion in aggregate service fees. Behind-the-meter generation accelerates deployment timelines beyond what grid interconnection alone would permit. Among the adjacent operators, Nebius is first to formalize a multi-hundred-megawatt fuel-cell program at this scale.
Aggregate feesup to $2.6B
Installed328 MW
May 20, 2026APLD
Applied Digital signs Polaris Forge 3 lease; crosses 1 GW contracted
15-year take-or-pay lease at fourth campus, Polaris Forge 3, signed with the same investment-grade hyperscaler that signed Delta Forge 1 in April. 300 MW critical IT against approximately 430 MW grid-connected capacity, more than 600 acres in a northern state. $7.5 billion base-term contracted revenue, up to $18.2 billion with renewal options. The portfolio now reaches four campuses and 1,200 MW of contracted critical IT, the first AI infrastructure operator in the thesis to cross 1 GW contracted. Total contracted lease revenue $31 billion across portfolio. The repeat-customer signal is unambiguous: same hyperscaler returned for a second 300 MW commitment four weeks later.
Lease value$7.5B base
Capacity300 MW
Total contracted$31B / 1.2 GW
May 20, 2026INDUSTRY
NVIDIA Q1 FY27: $81.6B revenue, $91B Q2 guide, $80B buyback authorized
Record revenue $81.6B (+85% YoY, +20% QoQ). Data Center $75.2B (+92% YoY). GAAP gross margin 74.9%. Q2 guide $91.0B +/- 2%, implying continued sequential acceleration. NVIDIA explicitly assumed zero Data Center revenue from China in outlook. $80B share repurchase authorization added; quarterly dividend raised from $0.01 to $0.25. Huang on call: every major hyperscaler partnering to deploy Vera Rubin. Positive demand signal across the NVIDIA-customer stack (CRWV, NBIS, IREN).
Revenue$81.6B
Q2 guide$91B
Data Center YoY+92%
May 26, 2026WULF
TeraWulf acquires Muskie campus in Eastern Kentucky, adding 1 GW second KY site
Acquired Muskie at the EastPark Industrial Park in Eastern Kentucky: 285 acres owned or controlled within a 1,000-acre park targeting 500 MW Phase 1 by H2 2028 and a second 500 MW Phase 2 by H2 2030. Kentucky Power (AEP subsidiary) building 345 kV substation on the 765 kV transmission network. Industrial General Service tariff. Permitting underway; zoned. Purchase price not disclosed. Energy service agreements signed concurrently. Total portfolio now spans six sites across four grid regions.
Capacity (target)1 GW
Phase 1500 MW / H2 2028
Total sites6
June 8, 2026APLD
Applied Digital signs Delta Forge 2; fifth campus lifts portfolio to $36B / 1.4 GW
15-year take-or-pay lease at a fifth campus, Delta Forge 2, in a new southern state. 210 MW critical IT, approximately $5.2 billion base-term contracted revenue, up to $12.7 billion with renewals across a 30-year term. The counterparty is the same U.S. high-investment-grade hyperscaler that signed Delta Forge 1 and Polaris Forge 3, making it the customer's third Applied Digital campus and 810 MW from a single counterparty. The portfolio now spans five campuses and 1,400 MW contracted against roughly 2.15 GW grid-connected, approximately $36 billion base-term contracted revenue (about $86 billion with renewals), roughly 70% backed by investment-grade hyperscalers. Initial operations early 2028. Financed alongside an upsized $550 million revolving credit facility and $1.59 billion of senior secured notes for a fourth building at Polaris Forge 1.
Lease value$5.2B base
Capacity210 MW
Total contracted$36B / 1.4 GW
June 8, 2026CIFR
Cipher Digital prices $810M Stingray project financing
Stingray Compute LLC, a wholly-owned subsidiary, priced $810 million of 6.000% senior secured notes due 2031 at 99.750% to fund the remaining build cost of the 100 MW Stingray facility in Texas and reimburse roughly $61.5 million of prior equity contributions. The Stingray site, in advanced lease negotiations with a preferred tenant, now carries dedicated project debt. Capital markets continue to finance the sites ahead of equity-analyst recognition.
Notes$810M
Coupon / due6.000% / 2031
June 8, 2026NBIS
Nebius commits ~£1.7B to UK NVIDIA infrastructure expansion
Approximately £1.7 billion across three new UK deployments of NVIDIA full-stack AI factory infrastructure, reaching 65 MW when fully ramped in 2027. Deepens the domestic footprint beyond the initial Longcross Park site and aligns with the UK AI Opportunities Action Plan. A regional footprint expansion rather than a change to the $44 billion Microsoft and Meta contracted base.
Investment~£1.7B
Capacity65 MW by 2027
June 11, 2026INDUSTRY
CoreWeave prices ~$3.5B of senior notes due 2032
$1.25 billion at 9.625% plus €2 billion at 8.500%, both maturing July 2032, roughly $3.5 billion combined. Continued capital-market access for the primary counterparty behind APLD and GLXY. Capital access is not the near-term question for CoreWeave; counterparty mix is.
Raised~$3.5B
Maturity2032
June 2026IREN
IREN expands to three continents and closes $3.65B investment-grade GPU financing
Completed the Nostrum acquisition (490 MW, Spain) on June 15 and announced a first Australian campus (800 MW at Bundey, South Australia, energization from 2028), taking the secured portfolio across three continents. Separately closed approximately $3.65 billion of investment-grade-rated debt ($1.5B delayed-draw term loan plus $2.1B senior notes) against the Microsoft contract, funding roughly 96% of the GPU equipment cost before the first Horizon hall came online.
GPU financing$3.65B (IG)
New capacity490 + 800 MW
June 22, 2026INDUSTRY
Microsoft to add ~2 GW with new Pecos, Texas datacenter campus
A multibillion-dollar campus of roughly 2 GW in Pecos (ERCOT) over five to seven years. Demand-side confirmation that hyperscaler capacity build continued through the summer rather than slowing.
June 30, 2026INDUSTRY
DOE issues fresh PJM emergency orders amid summer heat
Emergency orders 202-26-32 and 202-26-33 (later extended) direct dispatch and backup generation ahead of another Mid-Atlantic heat event, citing roughly 35 GW of unused backup generation nationwide. A second, larger order within six weeks of the May action turns a data point into a regime: campuses with behind-the-meter generation are treated as grid resources, not purely as demand.
July 1, 2026APLD
Applied Digital energizes second building at Polaris Forge 1; 175 MW live
Building 2 reached Ready for Service on schedule, adding 75 MW and lifting live capacity at Polaris Forge 1 to 175 MW against the 400 MW the campus is contracted to deliver at full build. Applied Digital remains the only operator in the thesis running AI infrastructure at this scale.
July 1, 2026INDUSTRY
NVIDIA unveils revenue-share and credit-support model to finance AI factories
A structure pairing NVIDIA product revenue with a share of cloud revenue and credit support to help finance third-party AI factories, with Sharon AI and Firmus among the initial partners. The chip maker is extending its own balance sheet to the neoclouds that lease from operators in this thesis.
July 6, 2026WULF
TeraWulf signs 20-year Anthropic lease (~$19B, 401 MW); sells Abernathy JV majority
A 20-year lease with Anthropic at the Hawesville, Kentucky campus, held through the Justified Data subsidiary: approximately 401 MW of critical IT and roughly $19 billion in contracted revenue over the initial term, with initial capacity in the second half of 2027 and the full 401 MW by early 2028. Anthropic is the first frontier AI lab to anchor a campus in this thesis directly. The same day, TeraWulf agreed to sell its entire 50.1% interest in the Abernathy joint venture to a Fluidstack-led group for roughly $530 million, monetizing an approximately $450 million investment at a premium and exiting Texas. The trade is a 25-year joint-venture lease it did not control for a wholly owned Kentucky campus with a frontier lab on it. Contracted revenue attributable to TeraWulf now stands near $27 billion.
Lease value~$19B
Capacity401 MW
Abernathy sale50.1% / ~$530M
July 6, 2026GLXY
Galaxy completes Helios Phase I; 133 MW delivered to CoreWeave
Full 133 MW of critical IT load (approximately 200 MW gross) delivered to CoreWeave on schedule, with rent commencement under the Phase I lease in Q2 2026. The 526 MW CoreWeave commitment spans 15-year leases with two five-year extensions and is expected to generate more than $1 billion in average annual revenue. Phase II (260 MW) deliveries begin in the first half of 2027; the campus now stands at 1.63 GW approved, up to 3.6 GW potential, across 2,200+ acres.
Delivered133 MW
RentCommenced Q2
July 15, 2026NBIS
Nebius opens an asset-light infrastructure partner model
Partners finance, own, and operate data centers built to Nebius specifications; Nebius supplies the systems architecture, software, and customer access in exchange for revenue share, licensing fees, commissions, and committed capacity. Initial arrangements are signed and unnamed. A GPU cloud monetizing scarcity it does not own.
July 17, 2026NBIS
Nebius closes first senior secured GPU facility, ~$775M
Maturing October 2030 at SOFR plus 250 basis points, secured on deployed GPU infrastructure and the contracted cash flows from an investment-grade customer. Combined with those cash flows, the facility covers more than 100% of the capital expenditure required to deploy the underlying GPUs. Nebius holds more than $40 billion of contracted revenue from investment-grade counterparties and expects to repeat the structure against the rest.
Facility~$775M
PricingSOFR + 250
Capex coverage100%+
July 20, 2026IREN
IREN signs $2.8B with AI developers; 2026 ARR target raised above $4B
New multi-year cloud contracts worth $2.8 billion in total value, adding Perplexity, Figure AI, Together AI, Fireworks AI, Fal AI, and Hume AI alongside Microsoft, NVIDIA, and Fluidstack. Year-end ARR guidance moves from $3.7 billion to more than $4 billion, roughly 85% under contract, against 480 MW of gross AI cloud capacity delivering this year. The contracts carry customer prepayments equal to about 45% of the associated GPU capital expenditure. Cash stood at $7.6 billion at June 30.
New contracts$2.8B
ARR target$4B+
Prepayment~45% of capex
July 22, 2026GLXY
Galaxy launches $3.507B Helios Phase II financing, disclosing a $10.4B lease floor
A Helios subsidiary launched $3.507 billion of senior secured notes due 2031 to fund two buildings and eight data halls in Dickens County, Texas: 400 gross MW, 260 MW of critical IT, rent targeted to commence in Q2 2027. The largest single project financing in the thesis to date. The offering materials put $10.4 billion of minimum contracted lease payments against Phase II alone, at a 13.7% starting gross yield on cost, near triple-net, with NOI margins above 90% and an inflation escalator floored at 3%. Galaxy's public figure for the full 526 MW commitment has been more than $1 billion in average annual revenue.
Offering$3.507B
Lease floor$10.4B
Yield on cost13.7%
July 27, 2026APLD
Applied Digital closes fiscal 2026 at 1,410 MW contracted and $36B of base-term revenue
Fourth-quarter revenue of $258.7 million, up 407%, against $611.3 million for the fiscal year and $107.2 million of adjusted EBITDA. The contracted portfolio stands at approximately 1,410 MW of critical IT across five campuses, roughly $36 billion over the initial 15-year base terms and roughly $86 billion if every renewal option is exercised. Beyond the contracted book and the 1.4 GW under construction, Applied Digital is marketing an additional 1.7 GW across multiple states. A memorandum of understanding with CoreWeave would assign the Polaris Forge 1 Building 4 lease to a CoreWeave subsidiary once that subsidiary carries an investment-grade rating, extending the credit-quality work begun with the springing guarantee and the A3 SPV.
Contracted1,410 MW
Base term$36B
FY26 revenue$611.3M
July 28, 2026GLXY
Galaxy closes the $3.507B Helios Phase II notes at 9.875%
Priced July 23 and closed July 28 at 99.500 of par, maturing August 2031, funding the two buildings and eight data halls in Dickens County against $10.4 billion of disclosed minimum lease payments. The coupon is the widest project financing in the thesis by roughly three percentage points. Applied Digital funded investment-grade hyperscaler leases at 6.750% and 7.000%, Cipher funded Stingray at 6.000%, and Cipher's Black Pearl paper backed by an Amazon guarantee priced at 6.125%. Same asset class, same year, same market. The spread is the tenant.
Coupon9.875%
Size$3.507B
MaturityAug 2031
July 29, 2026INDUSTRY
Alphabet and Microsoft report capex acceleration through the July cycle
Alphabet spent $44.9 billion on property and equipment in the June quarter against $22.4 billion a year earlier, a clean doubling, with Google Cloud revenue up 82% to $24.8 billion. Microsoft closed its fiscal year having added $115.9 billion of property and equipment against $64.6 billion the year before, and Azure passed $100 billion of annual revenue for the first time. These are the two quarters the capex-slowdown case pointed at.
Alphabet Q2 capex$44.9B
Microsoft FY26 capex$115.9B
August 3, 2026IREN
IREN closes the Mirantis acquisition
Approximately 12.6 million ordinary shares fixed at signing, plus roughly $40 million of cash, restricted stock units and other consideration at closing. Mirantis is an inaugural partner in NVIDIA's AI Cloud Ready initiative and has integrated its open-source k0rdent AI platform with NVIDIA DSX OS components. IREN says the capability has already supported several announced and prospective AI cloud contracts. The software layer sits on top of owned land, power, data centers and compute, which is the vertical stack IREN has been assembling in order.
Consideration~12.6M shares + ~$40M
August 4, 2026CIFR
Cipher delivers Black Pearl capacity two months early; rent commences
An amendment to the Black Pearl lease, executed at the investment-grade tenant's request, pulled initial delivery forward by two months. Capacity was delivered at the beginning of August and rent has commenced, the first HPC revenue in the company's history and the end of its pre-delivery status. A tenant that asks for capacity sooner is a tenant whose own demand arrived sooner. Cipher also secured an option on Apollo, roughly 288 acres within 25 miles of San Antonio carrying up to 900 MW, submitted as studied load through ERCOT's Batch Zero process. Average contracted annualized NOI rises to approximately $793 million, and the grid pipeline now runs to roughly 4.4 GW across eleven sites.
Early by2 months
Avg annual NOI~$793M
Portfolio~5.3 GW
August 5, 2026WULF
TeraWulf reaches 102 MW live and unlocks $600M of Google credit support
CB-3 completed in early July, lifting revenue-generating critical IT at Lake Mariner from 81 MW to 102 MW and satisfying the conditions for $600 million of Google's credit support for Fluidstack's lease obligations to become effective. Delivery is what converts a backstop from a promise into a claim. HPC leasing produced $31.9 million of the quarter's $44.8 million of revenue, roughly 71%. With the whole Abernathy interest under agreement to be sold, the contracted platform stands at 839 MW of critical IT across Lake Mariner and Justified, approximately $27 billion of contracted revenue and roughly $1.5 billion of average annual NOI. Cayuga now carries the Lake Hawkeye name and a 2029 delivery date, and Chesapeake cleared FERC authorization.
Live102 MW
Google support$600M effective
Contracted839 MW
August 5, 2026GLXY
Galaxy publishes Phase I economics and adds three Texas sites
The Data Centers segment recorded its first revenue quarter: $20 million of adjusted gross profit and $11 million of adjusted EBITDA, with all 133 MW of Phase I in service by quarter end. From the third quarter Galaxy expects Phase I alone to produce approximately $80 million of quarterly leasing revenue at project-level adjusted EBITDA margins above 90%, roughly $2.4 million per megawatt per year. The campus-wide figure moved with it, from more than $1 billion of average annual revenue across the 526 MW commitment to more than $1.2 billion. Post-quarter Galaxy acquired Merlin at McGregor (74 MW initial, up to 500 MW), Caspian (~700 MW) and Selene (~900 MW), taking the total power pipeline past 5.7 GW, with Helios III and Helios IV moving through ERCOT as separate gigawatt load requests.
Phase I revenue~$80M/qtr
Campus avg annual$1.2B+
Pipeline5.7 GW
August 10, 2026RIOT
Riot signs a 20-year, 191 MW lease with a frontier AI lab (~$9.1B)
One of the world's leading frontier AI labs took 191 MW of critical IT at Rockdale under a build-to-suit Tier 3 lease running through June 2048: approximately $9.1 billion over the initial term and $16.1 billion if both five-year extensions are exercised. Estimated cumulative NOI is $7.3 to $8.2 billion, an average of $365 to $411 million a year. The initial 96 MW is expected in December 2027 and the full 191 MW by June 2028, on interconnection already approved and energized. Morgan Stanley provided a $573 million interim facility to fund early development while an investment-grade credit backstop is finalized. Together with AMD's 50 MW, Riot holds 241 MW and roughly $9.8 billion of contracted revenue across two counterparties, having gone from the smallest contracted base in the thesis to the fifth largest in seven months.
Lease value~$9.1B
Capacity191 MW
Contracted total241 MW / ~$9.8B
August 12, 2026NBIS
Nebius books four billion-dollar AI cloud contracts; ARR reaches $3.0B
Revenue of $582.3 million, up 454%, with AI cloud at $574.9 million and a 50% adjusted EBITDA margin in that segment. Four contracts averaging more than $1 billion of total value each went to Reflection, Cohere, another U.S. AI neolab, and a large U.S. quantitative trading firm. The pricing is the disclosure that matters: annual contract value repriced from a $12 million per megawatt 2026 base to $20 to $25 million, roughly 70% of deals carried prepayments covering 50% to 60% of the associated capital expenditure, and the expected payback period compressed to one year and ten months from a two-to-three-year range. Short-term capacity is clearing at $40 to $50 million per megawatt in the third quarter. Year-end contracted power guidance rose again, to 5 GW, against deployment planned above 1 GW a year from 2027.
ARR$3.0B
ACV per MW$20-25M
Payback1yr 10mo
Fall 2026CIFR
Cipher Digital rent commencement at Barber Lake
Barber Lake (300 MW, Fluidstack backed by Google) targets initial delivery in September with rent commencing October 2026, following Black Pearl's August start. All long-lead equipment is secured and the tenant has taken partial occupancy. The contracted portfolio's $793 million average annualized NOI is measured from October 2026 through September 2036.
Mid-2026IREN
IREN Microsoft GPU deployment at Childress
200 MW critical IT load deployed across Horizons 1-4 at Childress, Texas for $9.7B Microsoft contract. 76,000 NVIDIA GB300 GPUs in liquid-cooled Tier-3 data centers. Target $1.94 billion annualized revenue.
Late 2026WULF
TeraWulf CB-4 phased delivery and rent commencement
The first CB-4 data hall has entered commissioning, with phased delivery and rent commencement expected across the second half of 2026 and CB-5 following in the first quarter of 2027. The two buildings carry 336 MW of critical IT between them at a build cost of $8 to $10 million per megawatt. The Abernathy exit proceeds arrive alongside, in three payments running to April 2027, the first $250 million of which landed in early July.
Late 2026NBIS
Nebius Mega Or Israel facilities begin delivery
First 22 MW at Masmiyya facility delivered. Beit Shemesh 58 MW facility begins phased delivery through early 2027. Combined 80 MW Israeli footprint from $880 million Mega Or build. Adds to Modi'in 8 MW operational since September 2025. Microsoft and Meta contracts generating revenue.