January 2026RIOT
Riot Platforms signs $1B AMD data center lease
First hyperscale data center lease at Rockdale, Texas with AMD. 10-year agreement for 25 MW with $311 million initial value, up to $1 billion with three 5-year extensions. AMD holds expansion rights to 200 MW total. Riot acquires 200 acres of Rockdale land for $96 million, funded by selling 1,080 BTC. Establishes 1.7 GW Texas data center portfolio.
Contract value$311M-$1B
Capacity25-200 MW
January 2026APLD
Applied Digital breaks ground on Delta Forge 1
Groundbreaking on 430 MW AI Factory campus in strategic southern U.S. market. Two 150-MW facilities spanning 500+ acres, designed to support 300 MW critical IT load. Leverages proprietary AI Factory blueprint refined at Polaris Forge. In discussions with prospective third investment-grade hyperscaler customer. Initial operations expected mid-2027.
Utility power430 MW
Target onlineMid-2027
January 2026GLXY
Galaxy Digital receives ERCOT approval for 830 MW expansion
Completes Large Load Interconnection Study for additional 830 MW at Helios campus in West Texas. Total ERCOT-approved capacity reaches 1.6 GW. Construction underway for Phase 1 delivery to CoreWeave in H1 2026. Campus expansion potential grows to 3.5 GW with additional land acquisitions.
New approval830 MW
Total approved1.6 GW
February 2026WULF
TeraWulf acquires Kentucky and Maryland infrastructure sites
Strategic acquisitions add 1.5 GW to portfolio. Kentucky site in Hawesville offers 480 MW with immediate power access, on-site substation, and 250+ buildable acres. Maryland acquisition of Morgantown Generating Station includes 210 MW operational generation with expansion potential to 1 GW and 250 buildable acres near Washington D.C. Total portfolio reaches 2.8 GW across five sites with 643 MW contracted and 2.2 GW owned pipeline.
Capacity added1.5 GW
Total portfolio2.8 GW
February 2026GLXY
Galaxy Digital Q4 2025: Phase I delivery imminent, Phase II construction started
Q4 2025 earnings confirm first Helios data hall delivery to CoreWeave by end of Q1 2026. Full 133 MW Phase I on track for H1 2026. Phase II construction already underway with earthwork, concrete, steelwork, and long-lead equipment orders placed. Additional 1.8 GW in ERCOT applications beyond approved 1.6 GW. Management describes Helios as "first step" in multi-gigawatt, multi-tenant, multi-campus platform vision.
Phase I133 MW Q1
Pipeline1.8 GW pending
February 2026CIFR
Cipher Mining closes $2B notes for Black Pearl at 6.125%
$2 billion senior secured notes due 2031 priced at 6.125%, one full point below the Barber Lake offering. 6.5x oversubscribed with $13 billion in orders across 200+ accounts. Fully funds Black Pearl construction. Includes $232.5M reimbursement of prior equity contributions. Three bond offerings now total $3.73 billion.
Notes$2.0B at 6.125%
Total debt raised$3.73B
February 2026CIFR
Cipher rebrands to Cipher Digital, sells JV mining sites to Canaan
Formal rebrand reflects completed pivot from Bitcoin mining to HPC infrastructure. Sold 49% interests in Alborz, Bear, and Chief mining JVs to Canaan in all-stock transaction. Bitcoin holdings reduced to 1,166 BTC with full exit planned by year-end. Only remaining mining operation is Odessa (207 MW, $0.028/kWh PPA through July 2027).
February 2026CIFR
Cipher Q4 2025: Construction on track, $669M NOI projected
Q4 earnings confirm both Barber Lake and Black Pearl on schedule and on budget. Management discloses $669M average annualized NOI from Oct 2026 through Sep 2036, rising to $754M by 2035. No additional equity anticipated for contracted developments. Unrestricted liquidity $754M. Pipeline expands to 3.4 GW with Stingray (100 MW) in advanced lease negotiations, Ulysses (200 MW, Ohio) with hyperscalers in diligence.
Projected avg NOI$669M/yr
Liquidity$754M
February 2026IREN
IREN Q2 FY26: $3.6B GPU financing, 1.6 GW Oklahoma campus
Q2 FY26 results show revenue miss ($185M vs $281M consensus) as Bitcoin mining declines faster than AI Cloud ramps. AI Cloud Services at $17M, up from $7M. Secured $3.6B GPU financing for Microsoft contract at sub-6% interest. Announced new 1.6 GW Oklahoma data center campus with power from 2028. Total secured power exceeds 4.5 GW. Prince George has $400M ARR contracted with $500M+ in negotiation.
GPU financing$3.6B
Total power>4.5 GW
February 2026NBIS
Nebius announces 9 new sites, surpasses 2 GW contracted power
Q4 2025 earnings reveal expansion from 7 to 16 global sites with 9 new locations across Missouri, Alabama, Oklahoma, Minnesota, France, Israel, and the UK. Total contracted utility power exceeds 2 GW, ahead of the >2.5 GW year-end target set in November. Target raised to >3 GW by year-end 2026. Majority of new capacity from owned data centers. B300 GPU deployment underway at new sites. ARR hits $1.25B, beating $900M-$1.1B guidance by 25%.
Total sites16
Contracted power>2 GW
March 2026APLD
Applied Digital prices $2.15B notes at 6.75% for Polaris Forge 2
Subsidiary APLD ComputeCo 2 LLC prices $2.15 billion of 6.750% senior secured notes due 2031 at 98% issue price. Proceeds fund 200 MW critical IT load at Polaris Forge 2 in Harwood, North Dakota. Notes secured by first-priority liens on substantially all subsidiary assets. Applied Digital provides completion guarantees. Offering closed March 10. Combined with $2.35B Polaris Forge 1 notes (9.25%), total project-level debt reaches $4.5B. Coupon compression from 9.25% to 6.75% in four months reflects execution confidence.
Notes$2.15B
Coupon6.75%
Total project debt$4.5B
March 2026NBIS
Nebius signs $27B Meta contract, largest in thesis
Five-year AI infrastructure agreement with Meta valued at up to $27 billion. $12 billion dedicated capacity across multiple locations, plus up to $15 billion additional available compute. One of first large-scale NVIDIA Vera Rubin deployments. Delivery begins early 2027. Expands November 2025 $3B agreement that was constrained by supply. Combined with Microsoft $17.4B, total contracted revenue exceeds $44B. Single contract exceeds pre-announcement market cap of ~$25B.
Contract value$27B
Total contracted$44B+
March 2026WULF
TeraWulf secures $500M bridge facility for Hawesville
364-day, $500 million delayed-draw senior secured bridge credit facility led by Morgan Stanley. Finances construction and development of Hawesville, Kentucky data center acquired February 2, 2026. First dedicated financing for the KY site. $100 million minimum liquidity covenant. Capital formation continues to pace site acquisition.
Facility$500M
Term364-day
March 2026NBIS
Nebius closes $4.34B convertible notes, fully funds 2026 capex
Proposed $3.75B offering on March 17, one day after Meta contract. Demand drove upsizing. Closed March 20 at $4.34B total: $2.59B of 1.25% notes due 2031, $1.75B of 2.625% notes due 2033. Nebius goes from zero debt to $4.34B. Combined with NVIDIA $2B equity and Meta prepayments, management states $16 to $20 billion 2026 capex is fully funded.
Notes$4.34B
2026 capex plan$16-20B
March 2026NBIS
Nebius approved for 1.2 GW Missouri campus, announces $10B Finland site
Independence, Missouri City Council approves Chapter 100 incentive for largest US AI factory campus: up to 1.2 GW on approximately 400 acres, over $650M in PILOT payments across 20 years. Separately, Nebius announces $10 billion data center in Lappeenranta, Finland with 310 MW capacity and first delivery in 2027. Largest site outside the US.
Missouri1.2 GW
Finland310 MW
March 2026CIFR
Cipher Digital signs third campus lease, closes $200M revolver
Executes 15-year lease with undisclosed investment-grade hyperscale tenant for third data center campus at an existing site. Contract value undisclosed. Third hyperscaler-grade counterparty in under a year. Separately closes $200M syndicated revolving credit facility with $50M accordion, led by Morgan Stanley, priced at SOFR +1.25% to 1.75% with leverage-tied step-downs.
Lease term15 years
Revolver$200M
Counterparties3
April 2026IREN
IREN Sweetwater 1 substation energization
1,400 MW bulk power station (345kV/138kV) energized at Sweetwater Hub in West Texas. One of largest digital infrastructure developments in the United States. Foundation for multi-gigawatt AI campus. Data hall delivery cadence of approximately 50 MW per month begins post-energization.
Mid-2026WULF
TeraWulf Lake Mariner HPC Phase 1 online
Approximately 40 MW critical IT load operational for Fluidstack at Lake Mariner, New York. First HPC colocation revenue at zero-carbon facility. Phased deployment continues toward 200+ MW total.
Fall 2026CIFR
Cipher Digital rent commencement at Barber Lake and Black Pearl
Barber Lake (300 MW Fluidstack/Google) targets rent commencement October 2026. Black Pearl (300 MW AWS) targets rent as early as Q4 2026. First contracted infrastructure revenue. Projected $669M average annualized NOI begins.
Mid-2026IREN
IREN Microsoft GPU deployment at Childress
200 MW critical IT load deployed across Horizons 1-4 at Childress, Texas for $9.7B Microsoft contract. 76,000 NVIDIA GB300 GPUs in liquid-cooled Tier-3 data centers. Target $1.94 billion annualized revenue.
Late 2026WULF
TeraWulf Abernathy JV facility online
168 MW joint venture with Fluidstack at Abernathy, Texas operational. $9.5 billion 25-year contract begins generating revenue. Google-backstopped credit enhancement reduces financing costs.
Late 2026NBIS
Nebius Mega Or Israel facilities begin delivery
First 22 MW at Masmiyya facility delivered. Beit Shemesh 58 MW facility begins phased delivery through early 2027. Combined 80 MW Israeli footprint from $880 million Mega Or build. Adds to Modi'in 8 MW operational since September 2025. Microsoft and Meta contracts generating revenue.